Construction Progress Greiner

 

Our new industrial building is starting to take shape. Construction measures are in time. The majority of foundations as well as the prefab concrete elements consisting of frameworks, pillars, beams, roof trusses and ceilings are installed. The shell is scheduled to be finished in the end of November 2019. The next construction phase will include concrete floors, interior construction, building services as well as draining and outdoor facilities.