Construction Phase: Shell Construction finished

 

Since the last update in October 2019, the prefab concrete elements and the roof were mounted. The roof is being sealed as well as windows and doors are placed. After sealing of the building envelope technical and interior construction work can be done in the winter months. Meanwhile the development for power, gas, water and telecommunication supply is done.

One of the last steps will be the outdoor facilities, like access roads and parking lots. The building is scheduled to be finished in May / June 2020.